Adding Prerequisite and Dependent Tasks
The Prerequisites/Dependents tab is used to associate other tasks with the current task, either as a prerequisite action or a dependent action. A prerequisite task is a task that must be completed before the current task can be completed. A dependent task relies on the current task being completed.
To Add a Prerequisite or Dependent Task:
- Open the task and choose the Prerequisites/Dependents tab.

- Choose Add in the Prerequisite Tasks group. Select a task in the prerequisite task list. Select the percentage that the chosen task must be completed before the current task can be started. Choose OK.
- Choose Add in the Dependent Tasks group. Select a task in the dependent task list. Select the percentage that the current task must be completed before the chosen task can be started. Choose OK.
- Choose OK to save your changes.
|